Please see attached .PDF for the full documentation.
Support KnowledgebaseUpdated August 2019Chain and Roller to Dual Belt Conveyor Conversion Process This document will walkthrough the process of converting a chain and roller system to a dual belt. Please notify Tommy Car Wash Systems prior to converting your site. 1.Close wash for planned downtime, typically 1-2 weeks. 2.Remove floor and excavate according to Belt Pit Plan, leaving wash equipment in place.
Support KnowledgebaseUpdated August 20193.Pour concrete on new pit floor . 4.Allow concrete time to cure. 5.Pour side wall
Support KnowledgebaseUpdated August 20196.Install new Tommy Transporter Belt Conveyor and reopen car wash.